HS2 completes civil engineering works on longest tunnel
23 Jan 2026The close of work on the tunnel's vent shafts brings an end to a project our Align JV began almost five years ago
Our HS2 Align joint venture hit a major milestone recently as Florence, one of two Tunnel Boring Machines (TBMs) cutting their way through the chalk and flint beneath the Chiltern Hills, completed her first mile.
Named ‘Florence’ by local school children, the TBM is one of two identical machines excavating the twin ten-mile-long tunnels. A second machine, named ‘Cecilia’ is a short way behind, with both TBMs expected to break out in around three years’ time.
Designed specifically for the geology of the Chilterns, each machine is a self-contained underground factory, digging the tunnel, lining it with concrete wall segments and grouting them into place as it moves forward.
The first two TBMs are operated by HS2’s main works contractor, Align – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick. A crew of 17 people keep the machines running, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.
Rohan Perin HS2 Ltd Project Client
The first two TBMs are operated by HS2’s main works contractor, Align – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick.
A crew of 17 people keep the machines running, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.
I am delighted with the progress that Florence has made since its launch in May, with Cecilia not far behind. All the spoil from the TBMs is converted into slurry before being pumped back to our South Portal site, just inside the M25, where it is processed and used for landscaping on site. This is, and will continue to be, a huge logistical challenge, as Florence and Cecilia continue their journey through the Chilterns. Florence reaching the 1 mile point is a great achievement, however we still have a long way to go.
Daniel Altier Align Project Director
Each of the separate northbound and southbound tunnels will require 56,000 precision engineered, fibre-reinforced concrete wall segments – which are all being made at the south portal of the tunnel, next to the M25. During her first mile, Florence and her crew have installed more than 5,500 separate segments, each weighing around 8.5 tonnes.
Approximately 2.7 million cubic metres of material will be excavated during the construction of the tunnels and used for landscaping around the south portal site. Once construction is complete, this will help create around 90 hectares of wildlife-rich chalk grassland habitats. Chalk grassland used to be widespread across the hills of south east England and are considered habitat of international conservation significance with just 700ha left across the Chilterns.
In total there will be ten TBMs on the HS2 project - working to create 64 miles of tunnel between London and the West Midlands including major tunnels on the approach to London and Birmingham.
More than 20,000 jobs and over 650 apprenticeships are already being supported by HS2, which is set to transform transport links between Britain’s major cities, free up space on the rail network for more freight and local services and support the UK’s transition to net zero carbon emissions.
The TBM is named after Florence Nightingale, the founder of modern nursing, who spent many years in Claydon, Buckinghamshire where she wrote books on nursing, with the name suggested by students at Meadow High School in Hillingdon.
The close of work on the tunnel's vent shafts brings an end to a project our Align JV began almost five years ago
The construction of the 10-mile tunnel by our Align JV finishes ahead of schedule
Iconic structure forms part of the HS2 project being constructed by our Align JV
The close of work on the tunnel's vent shafts brings an end to a project our Align JV began almost five years ago
As 2025 draws to a close, we explore key milestones, partnerships, innovative solutions and award-winning projects shaping the future of sustainable engineering and construction.
Members of our M6 and A19 teams were recognised for their acts of bravery and selflessness at the recent Highways Heroes Awards
Watch the team talk about the construction of new facilities at Tolworth Hospital, which are set to transform the way mental health care is delivered
The close of work on the tunnel's vent shafts brings an end to a project our Align JV began almost five years ago
Project partners gathered on level 37 to celebrate reaching the highest point at one of London’s most forward thinking and sustainable commercial developments