9th Nov 2026

Bringing down a giant

The removal of the tower crane at 2 Finsbury Avenue was one of the most complex dismantling operations ever undertaken in London

For more than two years, the innovative tower crane cantilevered from the East Tower core has been one of 2 Finsbury Avenue’s defining features.

Visible across the City and standing some 200 metres above the streets below, its installation was an engineering feat and helped shape the construction of one of London's most significant commercial developments, a JV between British Land, GIC and Modon as part of the Broadgate campus.

But what goes up must come down, and its removal involved one of the most complex tower crane dismantling operations ever undertaken in London.

Completed over five weeks this summer, the operation involved multiple organisations including specialist lifting contractors, three local authorities and teams from across Sir Robert McAlpine, and use of the largest crawler crane to enter the City of London.

An alternative approach

Having already established a robust methodology to climb down the tower crane, the team saw an opportunity to gain time and reduce programme risk by changing its approach and using a giant crawler crane supplied by Mammoet.

With a boom reaching almost 200 metres into the London skyline, it is the sort of crane you’d normally expect to see lifting wind turbines or working on large industrial projects.

It’s a methodology rarely seen in such a tight city-centre environment and one that required extensive planning, analysis and collaboration.

2FA Tower Crane Dismantling 3

Imaginative solutions

2FA Tower Crane Dismantling 2

Above ground, we had to navigate neighbouring buildings, narrow streets and some of the busiest transport routes in the capital. The crawler crane's location had to be carefully coordinated with existing infrastructure while bollards and other street furniture were temporarily removed to create the necessary working area.

Below ground, the situation was equally complex. The presence of a shallow Victorian gas main beneath part of the crane's operating footprint meant detailed geotechnical assessments and load modelling were required to understand how forces would be transmitted through the ground. The team designed a precisely engineered sand bed and load-spreading arrangement to ensure the crane could operate safely without exceeding allowable limits.

They also used purpose-designed, fabricated steel trusses to support the space between the tarmac and the crane’s boom, negating the need to transport and store shipping containers normally used for such purposes – an impractical solution for a constrained city centre site.

With safety at the forefront of the operation, and wind conditions dictating every move, progress was incremental. Continuous weather analysis ensured we were ready to mobilise and make the most of every available window before strengthening winds forced work to stop again.

One of the most challenging stages involved lowering the crane's 50-metre jib between neighbouring buildings with minimal clearance. Detailed tagline procedures were developed and reviewed, while bespoke lifting arrangements kept heavy equipment away from the façade. Where possible, components were combined into single lifts, reducing time spent operating in the most constrained areas.

Close collaboration with stakeholders

An operation on this scale required impeccable coordination between the project team, our in-house lifting experts at McAlpine Plant and Lifting, local authorities, utility providers, highways teams, neighbouring developments and specialist suppliers.

More than 100 people contributed to the planning and delivery of the works. From the earliest option studies to the final lift, every element depended on teams working together to solve problems, adapt to changing conditions and maintain a relentless focus on safety.

At the heart of that effort was our specialist Plant and Lifting Team. They spent well over a year evaluating options, challenging assumptions and breaking down an enormous engineering task into a series of smaller, manageable solutions. By integrating their specialist knowledge into our project team, we were able to smoothly execute such an ambitious operation.

The achievement is testament to our teams’ engineering expertise, planning capability and commitment to collaboration.

2FA Tower Crane Dismantling 4

Latest news

  1. Engineering the future of the British Museum

    26 Oct 2026

    We are delivering works to support the transformation of one of the world’s leading cultural institutions

    Read more about
  2. SRM CV appointed to Developer-Led Framework

    19 Oct 2026

    Sir Robert McAlpine Capital Ventures has secured a place on key lots in England, Scotland and Wales strengthening its ability to pursue major healthcare and public sector opportunities

    Read more about
  3. Major Works Framework appointment

    19 Oct 2026

    The National Framework for Major Works 2026 is the third generation of the major works framework.

    Read more about
View all news