22nd Jul 2020

Work progressing on HS2

Preparations continue at South Portal site for the arrival of the project’s giant tunnelling machines.

We are working on the scheme as part of Align, our joint venture with international infrastructure specialists Bouygues Travaux Publics and VolkerFitzpatrick, which has been contracted to deliver the HS2 Central 1 (C1) package.

C1 consists of 21.6km of high-speed rail infrastructure including a 3.37km viaduct, 16.04km twin-bored tunnel and five vent shafts handling both intervention and tunnel ventilation facilities.

Significant work has already started at Align’s main site, the South Portal, which is located to the West of London just inside the M25 and covers 136 acres.

Dedicated motorway slip-roads have been built to link the new site with the M25 and take construction traffic off local roads. As you can see from the pictures, excavation is already well under way of the launch site from which two 2,000 tonne, 170m long tunnel boring machines will start their journey under the M25, excavating the twin bore Chilterns tunnel through Buckinghamshire.

Work is also under way on the construction of a concrete precast plant where the 118,000 tunnel segments, each weighing on average 8.5 tonnes, will be made.

Spoil from the tunnels will be pumped as slurry back to a treatment plant, also currently under construction, where it will be treated before it is used for landscaping on-site.

Just south of the main site will stand the Colne Valley Viaduct, which will be the longest railway viaduct in the UK at 3.4km long. It will carry HS2 across the Grand Union Canal and surrounding lakes. The 1,000 segments required for the viaduct will also be made on site at the South Portal and a separate batching plant is under construction.

Find out more about HS2

  1. Significant HS2 milestone as Chiltern Tunnel complete

    07 Aug 2025

    The construction of the 10-mile tunnel by our Align JV finishes ahead of schedule

    Read more about
  2. Colne Valley Viaduct scoops two NCE Bridges awards

    05 Aug 2025

    Iconic structure forms part of the HS2 project being constructed by our Align JV

    Read more about
  3. Unique HS2 tunnel portal completed

    25 Apr 2025

    Our Align JV builds tunnel extensions for HS2 to stop sonic booms from 200mph trains entering the 10-mile Chiltern Tunnel.

    Read more about

Latest news

  1. Our commitment to the Armed Forces community recognised

    07 Nov 2025

    We were formally awarded our Armed Forces Covenant Employer Recognition Scheme Silver Award at an event at the Honourable Artillery Company in London

    Read more about
  2. New footage shows impressive progress at Agratas

    06 Nov 2025

    Agratas has shared dramatic aerial footage capturing construction progress at its battery manufacturing facility in Bridgwater, Somerset

    Read more about
  3. A military mission where everyone comes out a winner

    05 Nov 2025

    Following their recent addition to our family of charity partners, we're working with the Forces Employment Charity to strengthen our support for the Armed Forces community

    Read more about
View all news