3rd Aug 2020

Chiltern tunnels launchpad completed

Our Align JV celebrate a major milestone for the arrival of HS2’s first giant tunnel boring machines (TBMs) with the completion of the 17m high launchpad.

Preparation for the arrival of HS2’s first giant tunnelling machines has passed a major milestone with the completion of the 17m high headwall and ground reinforcement at what will become the south portal of the 10-mile long Chilterns tunnel.

A specialist team, led by our Align JV has spent seven months excavating more than 160,000m3 of material in order to create a level surface from which the two enormous machines will launch early next year.

Weighing in at 2,000 tonnes and stretching for 170m – the two tunnel boring machines (TBMs) are being built by world-leading German tunnelling specialists Herrenknecht and are due to arrive at the site, near to the M25, later in the year.

Alongside the excavation, a specialist team of subcontractors including Roadbridge and KV JV - formed from Keller Group plc and VSL International – have constructed a 17m high headwall through which the TBMs will break to begin their three-year long tunnel drive.

In order to reinforce the ground behind the headwall, more than 636 ‘soil nails’ – some up to 20m long – were driven into the wall and connected to the concrete lining. Each of the nails, consisting of steel or glass fibre reinforced polymer tendons, were inserted using a specialised drilling rig in a delicate operation which can take up two hours.

This reinforcement is required to hold the ground and the surface of the wall in place as the TBMs begin to break through.

Welcoming the milestone, Mark Clapp, HS2 Ltd’s C1 Senior Project Manager said: “Safety is of course our top priority. The new covid-19 processes and procedures put in place by Align ensured that we were able to keep to schedule while keeping everyone safe – and I’d like to thank the whole team for pulling together during what has been a difficult few months for the whole construction industry."

Align Project Director Daniel Altier added: “The completion of the soil nailing is a very visual example of how we are preparing our South Portal site for the arrival of the TBMs later this year. It is now clear for all to see where the TBMs will start their journey. 

"This has been a great team effort by all concerned, considering the challenges caused by Covid-19, including HS2, Align and our colleagues at Roadbridge and the KV JV.” 

Align is delivering the C1 portion of HS2 phase 1 which includes the 10 mile long (16km) twin bore Chilterns tunnel and the 3.4km Colne Valley Viaduct. 

Work on site was paused for four days at the start of the coronavirus lockdown in order to deep clean the work site and put in place new hygiene and social distancing procedures in line with government advice and industry best practice.

Once work is complete, the whole construction site will be landscaped with material excavated from the tunnels, and trees planted in order to blend it in with the surrounding countryside.

To find out more, please visit the Align JV website

Find out more about HS2

  1. HS2 completes civil engineering works on longest tunnel

    23 Jan 2026

    The close of work on the tunnel's vent shafts brings an end to a project our Align JV began almost five years ago

    Read more about
  2. Significant HS2 milestone as Chiltern Tunnel complete

    07 Aug 2025

    The construction of the 10-mile tunnel by our Align JV finishes ahead of schedule

    Read more about
  3. Colne Valley Viaduct scoops two NCE Bridges awards

    05 Aug 2025

    Iconic structure forms part of the HS2 project being constructed by our Align JV

    Read more about

Latest news

  1. Celebrating IWD2026 with Lauren McCarthy

    16 Mar 2026

    Lauren McCarthy, Sustainability Manager on the Therme project, details her path into the industry, and the importance of sustainability in construction

    Read more about
  2. Celebrating International Women's Day with Anjana Raj

    09 Mar 2026

    Anjana Raj, Company Social Value Manager, details the benefit of social value to the industry, and how she’s leading the charge to bring about the next generation of construction professionals

    Read more about
  3. Supporting International Women's Day

    08 Mar 2026

    We celebrate the role women continue to play in shaping the future of the industry on the occasion of International Women's Day.

    Read more about
View all news